The Nigerian National Petroleum Company Limited (NNPC) has challenged the Nigerian Independent System Operator’s (NISO) rationalization that gas provide constraints are contributing to Nigeria’s declining electrical energy technology, reporting about 10% growth in gas production volumes in 2026 12 months to this point.
In a press assertion issued in Abuja on November 6, 2026, NNPC mentioned its gas transportation community had no recorded constraints affecting deliveries to energy producing stations nationwide.
The clarification adopted NISO’s November 5 assertion attributing the decline in electrical energy technology to restricted gas availability for thermal energy crops and diminished water inflows into hydroelectric reservoirs.
NNPC reports 10% gas production growth
NNPC mentioned the gas transportation community operated by its subsidiary, NNPC Gas Infrastructure Company Limited (NGIC), stays out there to help deliveries to energy stations, with no transportation-related constraints recorded inside its community.
The firm attributed the ten% growth in gas production to the Federal Government’s gas improvement and monetisation agenda. It maintained that gas provide availability was not a problem and reaffirmed its dedication to supporting electrical energy technology via dependable gas provide and transportation.
The assertion, signed by Andy Odeh, Chief Corporate Communications Officer of NNPC Limited, partly reads:
- “NNPC Limited confirms that gas transportation network operated by its subsidiary, NNPC Gas Infrastructure Company Limited (NGIC), remains available to support deliveries to power generating stations Nationwide without any constraints. NGIC’s operational records do not indicate transportation-related constraints within its network that explain the current decline in electricity generation.”
- NNPC mentioned the provision of its transportation community ought to be assessed individually from gas production, industrial provide preparations and precise deliveries to particular person energy crops.
- It added {that a} correct evaluation of the technology shortfall must also study energy plant readiness, upkeep schedules and precise gas offtake.
The firm known as for a coordinated evaluate involving gas suppliers, transporters, energy turbines and NISO to determine the precise constraints.
NISO hyperlinks energy decline to gas shortages
In its November 5 assertion, NISO attributed the decline in electricity generation to limited gas availability for thermal power stations and reduced output from hydroelectric stations attributable to decrease water inflows into reservoirs.
The system operator mentioned the constraints had diminished electrical energy out there for distribution, leading to shorter provide hours and elevated load shedding throughout distribution networks.
- Insufficient gas had prevented some thermal producing stations from working at out there capability.
- Reduced water inflows had affected the output of hydroelectric stations.
- The affect different throughout the nation, relying on out there technology and electrical energy allocations to particular person Distribution Companies (DisCos).
NISO acknowledged the affect on customers and mentioned it was working to diversify the nationwide grid’s vitality combine to strengthen electrical energy provide safety.
TCN disputes Ikeja Electric’s outage declare
The disagreement follows earlier disputes over the causes of electrical energy disruptions. Nairametrics lately reported that the Transmission Company of Nigeria (TCN) accused Ikeja Electric of deceptive prospects by attributing feeder outages in elements of Lagos to grid instability.
TCN maintained that the disruptions have been largely attributable to diminished energy technology and faults on Ikeja Electric’s distribution community.
- TCN mentioned 68% of interruptions recorded on feeders supplying Ikeja Electric on November 1 and a couple of resulted from frequency-control load shedding attributable to low technology.
- Another 26% have been linked to Ikeja Electric’s non-compliance with load allocations or faults and upkeep on its community.
- The remaining 6% concerned TCN-planned upkeep, switching operations or line limitations.
Of 46 interruptions recorded on the 33kV feeders listed in Ikeja Electric’s discover, TCN attributed 29 to low technology and 14 to the distribution firm, with the remaining three linked to scheduled TCN upkeep.
TCN additionally cited Section 67 of the Electricity Act 2023, which it mentioned assigns NISO duty for figuring out the causes of disturbances and interruptions on the nationwide grid.
It urged DisCos to depend on verified data from NISO when explaining provide disruptions to prospects.